Hello, I have a problem: when a PC is turned off for a day due to the operator's absence, the next day when the PC is turned on, the scheduled backup for the previous day starts immediately, occupying the PC. Is it possible to tell the scheduler not to execute the missed scheduled backup if the previous backup was not performed?
thank you!
Paolo
Posts: 437
Threads: 61
Joined: Oct 2016
Reputation:
14
Hello Paolo,
Thanks for your question.
Your question makes a lot of sense to me and I certainly like the request.
As for "is this currently possible"? The answer sadly is "not at the moment".
I have logged a feature request for this on your behalf.
--
Wil
Posts: 437
Threads: 61
Joined: Oct 2016
Reputation:
14
Hi Paolo,
We have a ticket open for it as a feature request, so it will certainly be considered.
But we can't currently make any statements about upcoming features nor when they are released.
--